Many Brooklyn Heights Streets to be Milled and Paved Next Week

Brooklyn Community Board 2 has advised us that many Brooklyn Heights streets are scheduled for milling and repaving during daytime hours next week. The schedule is:

Remsen Street from the Promenade entrance to Clinton Street: Monday, June 25 and Tuesday, June 26.

Monroe Place, College Place, Love Lane, and Willow Street: Tuesday, June 26.

Middagh Street and Poplar Street: Wednesday, June 27.

Schermerhorn Street from Clinton to Court Street: Thursday, June 28 and Friday, June 29.

CB 2 provides this advice:

Vehicles left on these streets when work is ready to be performed will be relocated, generally within three blocks. DOT encourages owners of relocated vehicles to first walk around the neighborhood. If owners are not able to locate their vehicle, they may telephone their local precinct, 84 (718) 875-6811 or 88 (718) 636-6511 to learn where it was towed to.

Share this Story:

, , , , , , ,

  • Heights

    Finally Love Lane. It is such a mess

  • Banet

    What the hell? College Place is in essentially new condition and get ZERO traffic. Meanwhile, Grace Court Alley hasn’t been repaved in over 30 years. The tripping hazards there have tripping hazzards.

  • Andrew Porter

    This is just a ploy by NYC to keep those streets originally paved in cobblestones from showing their true natures…

  • https://www.youtube.com/watch?v=x7nPOzGeyaw Arch Stanton

    Good.